Northeast End-Around Taxiway, Package II
Dallas Fort Worth International Airport
Senior construction management of a $47 million end-around taxiway package delivered eight days ahead of schedule and approximately $1.5 million under budget.
- Role
- Senior Construction Manager
- Period
- August 2019 – March 2022
- Value
- $47M
- Status
- completed
Purpose
Package II of the Northeast End-Around Taxiway added taxiway pavement and supporting infrastructure that allow aircraft to route around the runway end rather than across it.
Engineering and delivery challenges
- Drilled-shaft foundations and a blast wall adjacent to active runway operations
- Integrating drainage, electrical, and airfield lighting with concrete taxiway paving
Role and responsibilities
- Senior construction management for the owner-representative team
- Field oversight of quality, schedule, and contractor coordination
Scope
- Concrete taxiway paving and drainage
- Drilled-shaft foundations and blast wall
- Electrical infrastructure and airfield lighting
Documented outcomes
- Delivered eight days ahead of schedule
- Completed approximately $1.5 million under budget
Work performed as part of multidisciplinary owner-representative teams on the DFW airfield capital program. Figures are as reported for the project and describe team outcomes.