Southwest End-Around Taxiway (SWEAT), Package 1B
Dallas Fort Worth International Airport
Element management of the principal construction package of the Southwest End-Around Taxiway program, opened to operations roughly one year ahead of the original milestone.
- Role
- Element Manager
- Period
- 2024–2026
- Value
- Approx. $250M of a $370M program
- Status
- completed
Purpose
End-around taxiways let aircraft taxi around the end of a runway instead of crossing it, removing runway crossings and improving both safety and airfield capacity. Package 1B delivered the core pavement, lighting, and electrical infrastructure of the Southwest End-Around Taxiway program at DFW.
Engineering and delivery challenges
- Environmental permitting under NEPA and coordination with the U.S. Army Corps of Engineers
- Construction sequencing on an active airfield with continuous runway operations
- Design coordination across civil, electrical, and airfield lighting disciplines
- Operational readiness and activation planning with airport operations and the FAA
Role and responsibilities
- Led the owner-representative project and construction management team for the package
- Coordinated design, construction, and stakeholder interfaces with the airport and FAA
- Managed schedule, cost, quality, and contractor performance through construction and activation
Scope
- Approximately 97,000 square yards of concrete pavement
- More than 600 LED airfield lighting fixtures
- Approximately 145,000 linear feet of electrical cable
Documented outcomes
- Operational opening completed in October 2026, approximately one year ahead of the original milestone
Work performed as part of multidisciplinary owner-representative teams on the DFW airfield capital program. Figures are as reported for the project and describe team outcomes.