Airport engineeringCompletedtaxiway

Southwest End-Around Taxiway (SWEAT), Package 1B

Dallas Fort Worth International Airport

Element management of the principal construction package of the Southwest End-Around Taxiway program, opened to operations roughly one year ahead of the original milestone.

Role
Element Manager
Period
2024–2026
Value
Approx. $250M of a $370M program
Status
completed

Purpose

End-around taxiways let aircraft taxi around the end of a runway instead of crossing it, removing runway crossings and improving both safety and airfield capacity. Package 1B delivered the core pavement, lighting, and electrical infrastructure of the Southwest End-Around Taxiway program at DFW.

Engineering and delivery challenges

  • Environmental permitting under NEPA and coordination with the U.S. Army Corps of Engineers
  • Construction sequencing on an active airfield with continuous runway operations
  • Design coordination across civil, electrical, and airfield lighting disciplines
  • Operational readiness and activation planning with airport operations and the FAA

Role and responsibilities

  • Led the owner-representative project and construction management team for the package
  • Coordinated design, construction, and stakeholder interfaces with the airport and FAA
  • Managed schedule, cost, quality, and contractor performance through construction and activation

Scope

  • Approximately 97,000 square yards of concrete pavement
  • More than 600 LED airfield lighting fixtures
  • Approximately 145,000 linear feet of electrical cable

Documented outcomes

  • Operational opening completed in October 2026, approximately one year ahead of the original milestone

Work performed as part of multidisciplinary owner-representative teams on the DFW airfield capital program. Figures are as reported for the project and describe team outcomes.