Project portfolio
Airport engineeringCompletedrunway
Runway 17R/35L Rehabilitation
Dallas Fort Worth International Airport
Senior project management of a $257 million rehabilitation of a 13,400-foot runway, returned to full service ahead of schedule and recognized as DFW's 2024 Project of the Year.
- Role
- Senior Project Manager / Element Leadership
- Period
- August 2023 – October 2024
- Value
- $257M construction
- Status
- completed
Purpose
Runway 17R/35L is one of DFW's primary arrival and departure runways. The rehabilitation renewed the pavement and supporting systems along the full 13,400-foot length while the rest of the airfield remained in operation.
Engineering and delivery challenges
- Phasing a full-length runway rehabilitation around an operating hub airport
- Holding an aggressive schedule tied to committed runway return-to-service dates
- Coordinating pavement, lighting, and NAVAID work with airport operations and the FAA
Role and responsibilities
- Senior project management and element leadership for the owner-representative team
- Oversight of design and construction coordination, schedule, quality, and contractor management
- Stakeholder interface with airport operations, airlines, and the FAA through phased reopenings
Scope
- 13,400-foot runway rehabilitation, including pavement and supporting airfield systems
Documented outcomes
- 9,275 feet of runway returned to service seven days early, on May 24, 2024
- Entire runway reopened ahead of schedule on October 11, 2024
Recognition
- DFW Airport Project Manager of the Year recognition, associated with this project
- DFW 2024 Project of the Year recognition
Work performed as part of multidisciplinary owner-representative teams on the DFW airfield capital program. Figures are as reported for the project and describe team outcomes.