Runway 17R/35L Rehabilitation

Dallas Fort Worth International Airport

Senior project management of a $257 million rehabilitation of a 13,400-foot runway, returned to full service ahead of schedule and recognized as DFW's 2024 Project of the Year.

Role
Senior Project Manager / Element Leadership
Period
August 2023 – October 2024
Value
$257M construction
Status
completed

Purpose

Runway 17R/35L is one of DFW's primary arrival and departure runways. The rehabilitation renewed the pavement and supporting systems along the full 13,400-foot length while the rest of the airfield remained in operation.

Engineering and delivery challenges

  • Phasing a full-length runway rehabilitation around an operating hub airport
  • Holding an aggressive schedule tied to committed runway return-to-service dates
  • Coordinating pavement, lighting, and NAVAID work with airport operations and the FAA

Role and responsibilities

  • Senior project management and element leadership for the owner-representative team
  • Oversight of design and construction coordination, schedule, quality, and contractor management
  • Stakeholder interface with airport operations, airlines, and the FAA through phased reopenings

Scope

  • 13,400-foot runway rehabilitation, including pavement and supporting airfield systems

Documented outcomes

  • 9,275 feet of runway returned to service seven days early, on May 24, 2024
  • Entire runway reopened ahead of schedule on October 11, 2024

Recognition

  • DFW Airport Project Manager of the Year recognition, associated with this project
  • DFW 2024 Project of the Year recognition

Work performed as part of multidisciplinary owner-representative teams on the DFW airfield capital program. Figures are as reported for the project and describe team outcomes.